Building a house in Costa Rica: the permits
The order of the paperwork to build: land use, alignments, water, CFIA plans on APC, the municipal permit, the construction tax and the INS policy.
Published October 26, 2026 · Updated November 3, 2026 · 9 min read
To build a house in Costa Rica, the order of the paperwork matters almost as much as the plans: each step uses documents from the one before, and a permit requested out of turn sends you back. This guide follows the sequence the official tools describe, with what the law and the CFIA say as of 3 November 2026.
Each municipality sets part of its own requirements. The CFIA advises checking yours before you start, and the examples here from Santa Ana and San José are not national rules.
The lot first: land use and alignments
The first document is the certificado de uso de suelo (land-use certificate), issued by the municipality. For building, it must state at least the use, setbacks, coverage, density, height, frontage and minimum area, plus its validity period (INVU Reglamento de Construcciones, art. 102). Before granting the permit, the municipality checks that the work conforms to that use, and also its exposure to natural hazards (art. 6). That INVU regulation applies where the municipality has none of its own.
Next come the alineamientos (alignments), the line from which you can build. Who issues them depends on what the lot borders:
- Facing a national road: MOPT, the public works ministry (art. 82).
- Facing a cantonal road: the municipality's roads department (art. 83).
- Next to rivers or protection areas: INVU, with an alignment valid for 24 months (art. 84).
- With springs: first an opinion from MINAE's Dirección de Aguas, then INVU (art. 85).
If you are still choosing land, the guide to buying a lot explains the protection areas around rivers and springs and what to check before you sign.
Water and electricity
Every building needs a disponibilidad de agua (water availability) document (Reglamento de Construcciones, art. 117). It is issued by AyA or the service operator; an ASADA (community water association) registered with AyA gives an availability letter; and for wells and springs, MINAE's Departamento de Aguas gives an availability or a concession. Confirm with AyA or your area's operator how that document is requested today.
The electric connection runs separately, with the distribution company. According to the CFIA help center, there is a provisional-connection form sealed by the CFIA and a definitive-connection form after a Declaración Jurada Eléctrica (sworn electrical statement). Santa Ana, for example, asks for an electricity availability letter only for condominiums, urbanizations, shopping centers and office complexes (Municipalidad de Santa Ana).
Plans and a contract with a CFIA professional
Only professionals incorporated in the CFIA (Colegio Federado de Ingenieros y de Arquitectos, the engineers' and architects' association) can authorize permit applications (Ley 833, art. 83, as reformed by Ley 9482 of 26 September 2017). Every construction plan carries the CFIA seal and the professional's registration number to be processed by public offices, and the CFIA will not seal it without the registration of the service contract and the construction stamp (Ley 4925, art. 54).
That contract is the contrato de consultoría (consulting contract): all professional-service contracts are registered through APC, the CFIA's digital platform for construction procedures (Reglamento APC, art. 12; Ley 4925, art. 53). The CFIA states in its help center that these obligations are mandatory legal rules, not mere recommendations. The APC seal is valid for one year (Reglamento APC, art. 20, reformed in 2024 and published in La Gaceta 231 of 9 December 2024); if it lapses, there are resello (re-sealing) rules in arts. 23 and 23 bis.
Plan review and the municipal permit
Institutional review
The portal tramitesconstruccion.go.cr, which the CFIA describes as the government's official portal for construction procedures, publishes the requirements by project type. For single-family homes, Decreto 36550, art. 3, points to section 2 of the portal's "Manual de Subclasificaciones" (sub-classification manual), and compliance is certified by the responsible professional in a sworn statement. Institutions have up to 15 business days to review the plans; if they do not do so in time, the plans are deemed reviewed and approved (silencio positivo, positive silence), with exceptions such as projects in the Zona Marítimo Terrestre, the coastal zone (Decreto 36550, arts. 10 and 14).
The municipal permit
Every construction work in populated areas needs a municipal license (Ley 833, art. 74). The license causes fees (art. 78) that must be paid for it to take effect (art. 79). Municipalities connected to APC work in "mixta" (mixed) or "digital" mode, according to the CFIA.
Once the municipality approves, the APC file moves to "Pendiente de Pago Municipal" (pending municipal payment). According to the CFIA help center, at that stage the INS policy is issued from APC and presented at INS offices to compute the payment, and then the municipal payment voucher and the policy certificate are uploaded to APC.
What the permit costs
CFIA charges
These are the charges the CFIA help center publishes, checked on 3 November 2026, computed on the value of the work:
| Charge | Amount |
|---|---|
| Construction stamp (Ley 4925, art. 57) | 0.100% |
| Derecho de asistencia (assistance fee) | 0.150% |
| Registration coupon | 0.0150% |
| APC administration, work estimated under ₡10,000,000 | ₡5,000 |
| APC administration, work of ₡10,000,000 or more | ₡20,000 |
Social-interest housing and State works are exempt from the APC administration charge. Plans made abroad pay a construction stamp of 1% of the value of the work (Ley 4925, art. 57, subsections d and h).
The municipal construction tax
The well-known "1%" is not a fixed national tax. Ley 4240, art. 70, authorizes municipalities to charge "hasta el 1% sobre el valor de las construcciones" (up to 1% of the value of the constructions), and each municipality decides how it applies it. Santa Ana, for example, charges 1% of the municipal engineer's valuation: for a ₡5,000,000 valuation, the tax is ₡50,000 (Municipalidad de Santa Ana). Ask your municipality for its rate and the value it applies it to.
The professional's fees are separate. For dirección de obra (construction supervision), the CFIA cites a minimum fee of 5% of the final value of the work under the Arancel de Servicios Profesionales de Consultoría para Edificaciones, its fee schedule for building consultancy (CFIA help center, checked on 3 November 2026).
Key fact: if you will finance the construction, the bank has its own requirements and costs. The guide to home loans and the housing bonus goes over them.
The INS policy and what we could not confirm
The Código de Trabajo (labor code) requires every employer to insure workers against work risks with INS, the national insurance institute (Ley 2, art. 193). That insurance is mandatory, universal and compulsory (art. 201), and public officials may not sign contracts or grant permits unless the work-risk insurance is presented first (art. 202). That is why the policy shows up inside the permit process.
Two points come up often that we could not confirm as a national rule:
- CCSS registration. Santa Ana asks for an INS statement and for being current with the CCSS (the social security fund), and says the municipality checks the CCSS; San José asks the applicant to be current with the CCSS if registered as an employer (Municipalidad de San José). We found no rule that makes registering the work with the CCSS a legal requirement for the permit nationwide. Confirm it with your municipality and the CCSS.
- Occupancy or habitability permit. We found no national occupancy certificate in the rules reviewed. Banks and municipalities may ask for a final inspection, but we did not verify its legal basis: ask what your municipality requires and, if there is a loan, your bank.
Minor works and construction supervision
Minor works
Minor repairs, remodelings and extensions that do not exceed ten salarios base (a legal reference salary) do not need a CFIA professional, but they do need a municipal license under each municipality's minor-works regulation (Ley 833, art. 83 bis). Work that, in the municipal official's technical judgment, modifies the structural, electrical or mechanical system and puts occupants at risk does not count as minor work. If new minor-work applications for the same property arrive within 12 months of a minor-work permit, the municipality inspects and denies the permit if it determines a major work is being split up. Confirm the current amount of the limit with your municipality.
During the work
Ley 833 places oversight of the work on the municipality (art. 87) and on the responsible professional, who has "la obligación de vigilar las obras" (the duty to oversee the works) (art. 83). In the dirección de obra the CFIA regulates, the professional checks the work at least every 7 calendar days and does the final handover together with the owner (CFIA help center). The documents, including the approved plans, the municipal permit and the CFIA's bitácora de obra (site logbook), must stay on site (Reglamento de Construcciones, art. 10).
If you are still looking for where to build, on Porta you can search land for sale, see prices in colones or dollars with the Central Bank exchange rate, and save lots to favorites to compare them calmly. Porta does not process permits or review plans: your professional, the CFIA and the municipality do. When you buy the land, check the closing costs.
Sources
- SINALEVI: INVU Reglamento de Construcciones, accessed 3 November 2026.
- Trámites Construcción: requirements portal, accessed 26 October 2026.
- CFIA: Help center, electric connection, accessed 3 November 2026.
- Municipalidad de Santa Ana: Construction permit procedure, accessed 3 November 2026.
- SINALEVI: Ley 833, Ley de Construcciones, accessed 3 November 2026.
- SINALEVI: Ley 4925, Ley Orgánica del CFIA, accessed 3 November 2026.
- CFIA: Reglamento APC, accessed 3 November 2026.
- CFIA: Help center, consulting contracts, accessed 3 November 2026.
- SINALEVI: Decreto Ejecutivo 36550 on plan review, accessed 3 November 2026.
- CFIA: Help center, municipalities on APC, accessed 3 November 2026.
- CFIA: Help center, municipal payment and INS policy, accessed 3 November 2026.
- CFIA: Help center, paying the construction permit, accessed 3 November 2026.
- CFIA: Help center, procedure charges, accessed 3 November 2026.
- SINALEVI: Ley 4240, Ley de Planificación Urbana, accessed 3 November 2026.
- CFIA: Help center, construction supervision, accessed 3 November 2026.
- SINALEVI: Código de Trabajo, Ley 2, accessed 3 November 2026.
- Municipalidad de San José: Construction work requirements, accessed 3 November 2026.
This guide is for information only and does not replace advice from a lawyer, notary, accountant or lender. Figures and requirements were checked against the linked official sources on November 3, 2026; confirm them before you decide.
Written by the Porta team with the help of artificial intelligence tools and checked against the sources cited in the text. If you spot an outdated figure, write to us from the Help Center.
Ready to look at lots? Filter land for sale by area and price.
See lots for saleRelated articles
Buying and financing
Buying a lot in Costa Rica: what to check
Plano versus finca, registry certificates, land use, water, easements, subdivision rules, river setbacks, the coastal zone and SETENA before you buy a lot.
October 26, 2026 · 11 min read
Buying and financing
Home loans and the housing bonus in Costa Rica
Colones or dollars, the TBP and TPM, what banks finance, insurance, early payment fees and the 2026 Bono Familiar de Vivienda, with every figure dated.
October 26, 2026 · 11 min read
Buying and financing
Closing costs and taxes when buying property
What you pay beyond the price: the 1.5% transfer tax, Registro fees, stamps, notary fees, property tax, capital-gains withholding and the registry alert.
October 26, 2026 · 10 min read